The Construction of above line from Km. 30 to Km. 120 between Katra Laole shall be undertaken by Konkan Railway Corporation Ltd., which includes construction of tunnels, major bridges and other civil engineering work such as Earthwork in cuttings / embankments and minor bridges. The entire Railway line has to be completed in the tight target period. For the purpose of convenience and easy handling, work of earthwork in cuttings / embankment and construction of minor bridges is grouped into number of packages.
Salient features of the proposed works of Earthwork and minor bridges will be:
1.
The work includes earthwork in cuttings / embankments for 90 lacs cum (approx.)
and construction of 30 minor bridges (approx.).
2. Earthwork in cutting is to be carried out in all types of soils / rock and as per the slope design.
3. The work may include slope protection works depending on the soil strata, such as shotcreting, boulder netting, rock bolting, soil nailing and concrete retaining wall etc.
4. The earthwork in embankment will be with compaction layer by layer.
5. Minor bridges may be with RCC/slab / hume pipe / any other type.
6. The bridge foundations can be either with piling / open foundation depending on the strata available. However, foundations will be standardized for the variable geological conditions.
7. As this is an earthquake prone zone, all structures will be designed for earthquake resistance.
8. Method of construction will be standardized.
It is proposed to select Contractors who are prepared to take the challenge and work along with us as empowered technical partner, who will be selected on the basis of information to be submitted along with supporting documents in prescribed format for pre-qualification of contractors for undertaking proposed works.
Following information for screening has to be submitted without fail:
a) Details
of earthwork and minor bridges carried out and completed / in progress during last 5
years.
b) Number
of projects where work is completed in time with clients certificates.
c) List
of machinery owned by the Contractors.
d) Details
of professional organization - man power with bio-data of professional staff.
e) Capability
to design the structures.
f) Financial
status of the company including balance sheet for last 5 years. Turnover of the company
during the last 5 years (cumulative) should be Rs.50 Crores.
g) Details
of Arbitration cases, Court cases/ disputes for the works executed during last 5 years.
h) Experience
if any, for executing the works in Himalayas.
The
above details should be submitted in the prescribed format on Excel Sheet, on a CD/Floppy
and one set of hard copy duly signed by the authorized signatory.
For
pre-qualifying the contractors following weightages will be given against each
item/strength of the contractors:
Sr.
No. |
Items |
Unit
for Assessment |
%
Weightage |
||||
1 i. |
Work
done experience during last 5 years- A)Minimum
two works of earthwork or minor bridges or combined together completed each costing
not less than Rs. 3.0 Crores Or B)
One work of earthwork or minor bridges or combined together completed costing not less
than Rs 6.0 Crores. |
No. of works |
40 |
||||
ii. |
Works
in Progress: A)Minimum
2 works of earthwork or minor bridges or combined together in progress costing not less
than Rs.3 Crores each or Rs 10.0 crores cumulative. Or B) Single work of earthwork or minor bridges or
combined together costing not less than Rs.10.0 Crores. |
No.
of works |
15 |
||||
2 i.
|
Capability
to design the structure In house design organization consisting minimum of
competent 1 post-graduate Engineer (structures) and 2 graduate Engineers. |
No.
of Design engineers. |
05 |
||||
3 |
Availability
of machinery minimum number of plant and equipment to be owned by contractor is as
per Annexure
|
No.
of machinery. |
10 |
||||
4 |
Availability
of professional man power minimum number of key personnel required is as per
Annexure
|
No.
of Personnel |
10 |
||||
5 |
Financial
status. Turnover during last 5 years Rs.100 Crores (Cumulative) |
In
Crores |
10 |
||||
6 |
Number
of Arbitration/ disputes/ court cases in the last 5 years. |
Number
of cases : i.
Nil
Case ii.
Upto
2 cases iii.
More
than 2 cases |
0 -5 -10 |
||||
7 |
Experience
of any work in Himalayan region including
works in progress. |
No.
of works & their value in Crores |
10 |
||||
TOTAL |
|
||||||
NOTES:
c. The applications for pre-qualification shall
be submitted at the following address.
The
General Manager (Projects)
Konkan
Railway Corporation Ltd.
Raigad
Bhavan, 8th Floor
Plot
No. 4, Sector 11
CBD,
Belapur
Navi
Mumbai 400 614
g. Base Year and Escalation
h. The Agency is informed that only factually correct
information is to be furnished. In the event of detection of incorrect information, the
Agency is liable to be summarily disqualified or terminated or black-listed.
Note
: Please see
the Annexures.